Site Decomissioning & Disconnect - Denver, CO
Decommission cabinets at existing Sprint sites:
Verify that OSP has cut all fibers connecting the JBox to the main cabinet.
Ensure power has been removed from cabinet.
Cut the power cables within the JBox below the cabinet.
Pull the power cables through the Panduit and coil them up in the cabinet. Remove the power connections to all the equipment in the cabinet.
Disconnect the Panduit from the main cabinet.
Unbolt the cabinet from the H-Frame.
Cap off or tape up the Panduit.
Take the cabinet and all equipment removed from the cabinet back to the Warehouse, clean and prepare for shipment.
Site Counter
Cabinets Installed
Cabinets Decommissioned
Fiber Optic Cable Pulled
82
n/a
82
n/a