Site Decomissioning & Disconnect - Denver, CO

Decommission cabinets at existing Sprint sites:

  • Verify that OSP has cut all fibers connecting the JBox to the main cabinet.

  • Ensure power has been removed from cabinet.

  • Cut the power cables within the JBox below the cabinet.

  • Pull the power cables through the Panduit and coil them up in the cabinet. Remove the power connections to all the equipment in the cabinet.

  • Disconnect the Panduit from the main cabinet.

  • Unbolt the cabinet from the H-Frame.

  • Cap off or tape up the Panduit.

  • Take the cabinet and all equipment removed from the cabinet back to the Warehouse, clean and prepare for shipment.

Site Counter
Cabinets Installed
Cabinets Decommissioned
Fiber Optic Cable Pulled

82

n/a

82

n/a